Jean-Drapeau

Work underway at Jean-Drapeau station

Project summary


Duration of the work: september to december 2021

Description of the work: renovation of both entrance building roofs

Métro impacts: No

Bus impacts: No

Impact on customer trips

All entrance building accesses will remain open, and no impact is expected. Areas for equipment storage will be sectioned off around the entrance buildings, but they will not obstruct any movement.

 

Impact on local residents

The work will be conducted Monday to Friday, during the hours authorized by the borough, and no impact on local residents is expected.

Learn more about the project

This project will include the following phases:

  • Demolishing the existing rooftop waterproofing system
  • Installing the new rooftop waterproofing system
  • Replacing the roof drains

The worksite in images

Top of page