Rielle mechanical ventilation station

Expansion of the Rielle mechanical ventilation station

The mechanical ventilation station (MVS) north of Wellington Street will be modernized. It will be expanded and brought up to current equipment standards.

parlons·en

Good neighbour committee

Would you like to take part in the Good Neighbor Committee for the Rielle mechanical ventilation station expansion project?

Click here to complete the application form by January 31, 2025.

Texte important

A public information session took place on January 16, 2025 to present the work.

Consult the presentation (French only).

See the recording of the information session (French only).

Project summary

Duration of the work: Beginning of 2025 to December 2027

Description of the work : Expansion of the Rielle mechanical ventilation station

Stay informed

Stay informed of the project’s progress and other events by signing up for the electronic newsletter

Description of the work

Preparatory work will take place in the parking lot between 252 and 290 Gordon Street.

Bell overhead cable relocation:

  • Bell will remove its existing lines from the worksite and maintain service with a temporary bypass. All communications about this will be handled by Bell.
Activity Date
Preparatory work
Fall 2024
Worksite opening
(fencing installation, worksite trailer placement)
Winter 2025
Pile driving and excavation
Winter 2025
Concrete work
Summer 2026
Equipment installation, landscaping
Fall 2027

The expansion and upgrading work will result in the following improvements:

  • The MVS will be much quieter thanks to more powerful noise suppressors. It will comply with all Verdun Borough noise by-laws.
  • With its clay brick exterior, the building will blend in seamlessly with the surrounding architecture.
  • The landscaping will cover more space and have a more diverse range of plants.
  • The green spaces and permeable pavers will provide eco-friendly water management by allowing rain to drain into the ground.
  • Tunnel ventilation will be more powerful and efficient.

Impact on local residents

The project will involve pile driving and soil and rock excavation.

  • We’ll update this page with the excavation method once it’s been chosen. Micro-blasting will not be used.
  • The excavation may generate vibrations big enough to be noticed by residents living near the worksite. That’s why we’re requiring the contractor to hire a specialized firm to conduct inspections (including taking photos) of buildings in the area. These inspections will document the condition of the buildings before and after the work. Property owners affected will be notified accordingly.
  • The firm hired by the contractor will also have to monitor the vibrations generated by the work using a device called a geophone. This is intended as a preventive measure. Data will be collected and analyzed in real time to ensure compliance with vibration limits.


In accordance with municipal by-laws:

  • The work will mainly be scheduled on weekdays between 7 a.m. and 7 p.m. To keep the project on schedule, some work may occasionally continue on weekends between 8 a.m. and 5 p.m.
  • On rare occasions, overnight work will be carried out while the métro is closed. Residents should not be affected by this work, as it will be done inside the tunnel.

To limit the impact on the neighbourhood, the following mitigation measures will be in place to reduce worksite noise:

  • Temporary noise barriers at least 3 metres high will be installed all around the worksite.
  • We will develop and implement a noise management program so that all worksite activities are within authorized noise limits.
  • Electrical equipment will be used where available to reduce noise at the source.
  • Crews will use vehicles and machinery with variable-volume backup alarms.
  • Noise levels will be monitored at the site.
  • The noise barriers installed around the worksite perimeter will keep dust inside the work area.
  • Worksite fencing with anti-dust sheets will be installed at the entrance.
  • The site will be hosed down during the demolition work to keep dust on the ground.
  • Site access roadways will be cleaned during the work.

From start to finish:

  • Gordon Street will stay open to traffic, but some parking spaces will be blocked.
  • Flaggers will be present during more critical operations and for a few days of work in public areas.
  • The De la Cours alleyway will remain accessible at all times.
  • Two trees were removed from the site and replanted elsewhere in the neighbourhood.
  • Some six trees had to be felled.
  • Others were only trimmed to avoid damage during the work.

We are committed to limiting the environmental impact of our work. Each tree was analyzed to find solutions other than felling. We always try to transplant existing trees if they have good chances of survival.

New trees, shrubs and greenery will be planted after the work to enhance the space and leave it in good condition, as per borough requirements.

Texte important

A public information session was held on January 16, 2025 to present the project, the work and the mitigation measures.

Consult the presentation.

Learn more about the project

A mechanical ventilation station is an infrastructure that is equipped with two fans designed to extract hot air from the métro network through inlets fitted with air vents. Huge noise suppressors mitigate the noise from these fans to ensure quiet for residents living close to a ventilation station.

Mechanical ventilation stations serve three essential purposes:

Comfort ventilation
Regulates the ambient temperature and supplies fresh air for transit users by exchanging air from the outside with air inside the métro network.

Night-time ventilation
Ensures a supply of fresh air for night workers carrying out routine maintenance.

Emergency ventilation
In the event of an incident, controls smoke and provides a safe evacuation route for passengers via the nearest métro station and ensures unobstructed access for emergency first responders.

Texte important

A public consultation was conducted for this project. Click here for more information.

Top of page